Facilities Notifications

Oriental Institute-Interior Courtyard fa├žade repairs

May 11, 2022

Mobilization will start on Friday, May 13, at 7 a.m. at The Oriental Institute, interior courtyard. There will be site fencing and scaffolding installed in preparation for façade repairs and restoration that will continue throughout the summer. The below graphic shows the schedule of work at the site. Please note, summer construction will start on Monday, June 6.

The campus community can expect the following:

  • The use of construction vehicles and a hoist will be ongoing.
  • A noise and dust mitigation plan will be followed throughout construction.
  • Workers will be on site each day until 3:30 p.m.; Saturday work will be scheduled, as needed.

For questions, please contact Patrick Lummen, project manager, at 616.437.3755 or plummen@uchicago.edu.


Bartlett Commons - Phase 1 Facade improvements

May 9, 2022

At 7 a.m. on Wednesday, May 11, mobilization will start at Bartlett Commons. There will be site fencing and scaffolding installed in preparation for façade repairs and restoration that continues throughout the summer. The below graphic shows the schedule of work at the site. Please note, summer 2022 is phase 1 of the project and phase 2 is scheduled for spring/summer 2023. The building will be a construction site through Sept. 2023.

The campus community can expect the following:

  • The use of construction vehicles and a crane will be ongoing.
  • A noise and dust mitigation plan will be followed throughout construction.
  • Walkways will be temporarily unavailable as shown in the graphic; signage will inform pedestrians of alternate routes.
  • Workers will be on site each day until 3:30 p.m.; Saturday work will be scheduled, as needed.

For questions, please contact Patrick Lummen, project manager, at 616.437.3755 or plummen@uchicago.edu.


How Do I?

UChicagoSocial: Facilities Services

{/exp:channel:entries}