Prioritized Crosswalk Enhancements

July 16, 2025

In order to further improve the safety of pedestrians throughout campus, there will be MMA painting and flexible bollards added to a number of existing crosswalks. Locations where this painting and flexible bollards are shown are shown in the graphic below. The crosswalks furthest south will be completed first, with the contractor then moving northbound, finishing the scope on 55th last.

Schedule:

Start: Beginning the week of July 21st
The work will continue through the Week of August 4th

Construction Impacts/Disruptions: Throughout the project, campus occupants and visitors can expect the following:

  • Temporary barricades as needed when working near the respective crosswalks.
  • Crosswalks will remain open during this time.

Crosswalk work graphic

For questions and concerns, please reach out to Lindsay Haskins,  Project Manager, lhaskins@uchicago.edu