June 27, 2025
This project is an interior renovation to add/upgrade the catwalk/fall protection system.
Schedule:
Start: July 7, 2025
Mobilization will begin Monday, July 7th. The project will be complete by Friday, August 22, 2025.
Construction Impacts/Disruptions: Throughout the project, building occupants, neighbors, and visitors can expect the following:
- Temporary storage unit located in the parking lot, on the south side of the lot, taking approximately one (1) parking spot. This will be delivered on Tuesday, July 1, 2025.
- The storage unit will remain until September 1, 2025.
For questions, please contact Andrea Herring, Project Manager, at aherring@uchicago.edu.