Main Quadrangle Paver Project – Hutchinson Court

August 21, 2025

We’ve reached a point in the project schedule where we will be pouring concrete. During the last of the concrete pours needed for the project, there will be a period of time in the afternoon of August 27th, where the concrete truck will need to be positioned outside of the construction fence, as shown on the graphic below.  

Schedule:

Anticipated Duration of Concrete Pours: Both Tuesday, August 26th, and Wednesday, August 27th, with the pedestrian pathway impact as illustrated below estimated to occur between 2 PM-4 PM on Wednesday, August 27th. All other times, the truck will perform pours within the project’s fencing.

Construction Impacts/Disruptions: During the time of the pour, the campus community can expect the following:

  • Concrete Trucks are arriving and leaving the project site as frequently as every 45 minutes for the day.
  • Flaggers present with the Concrete Truck to help navigate to the project site.

Hutch court graphic

For questions and concerns, please reach out to Lindsay Haskins,  Project Manager, lhaskins@uchicago.edu


How Do I?

UChicagoSocial: Facilities Services