July 15, 2025
To ensure the safety and reliability of campus infrastructure, the existing fire sprinkler system piping located between Cobb Hall and Levi Hall is being replaced. Details of the pedestrian pathway closures can be found in the graphic below.
Schedule:
- Start: Mobilizing the week of July 21st
- The work will continue through the middle of August 2025.
Construction Impacts/Disruptions: Throughout the project, building occupants and visitors can expect the following:
- Anticipated working hours will be from 7AM to 3PM
- Noise at the basement level when the new piping is being routed through the tunnel.
For questions and concerns, please reach out to Lindsay Haskins, Project Manager, lhaskins@uchicago.edu