June 9, 2025
The project will reconfigure the existing accessible NE entrance and vestibule doors to provide wider accessible openings with new automatic door operators, including push-plate actuators and card readers. The work will occur on the first floor exterior and interior areas of the existing NE entrance and vestibule.
Schedule:
Start: Wednesday, June 11th, 2025
The work will continue through middle of August 2025.
Construction Impacts/Disruptions: Throughout the project, building occupants and visitors can expect the following:
- Impact on NE Entrance ingress/egress and accessible route
- Workers will be on site from 6 a.m. to 2:30 p.m. each day
- Noise and Vibration impact from 6 a.m. to 2:30 p.m. each day
For questions and concerns, please reach out to: Bryndis Pape, Project Manager CPD at bpape1@uchicago.edu.