Facilities Notifications

WCCUP Chiller & Infrastructure Upgrades October 2025

October 7, 2025

On Tuesday, October 14, 2025, through Friday, October 31, 2025, construction activities related to the installation of a new chiller at WCCUP will occur. The use of a crane will be required for to complete the work.

Schedule:

  • Start: October 14, 2025
  • Finish: October 31, 2025
  • Work is scheduled to occur on weekdays from 6AM – 6PM.
  • No construction activities are expected to occur on the weekends.

Construction Impacts/Disruptions: Throughout the project, building occupants and visitors can expect the following:

  • Temporary road closure and no parking on S. Maryland Avenue.
  • Temporary sidewalk closures on the east side of S. Maryland Avenue, adjacent to WCCUP.
  • Material staging along 56th Street.
  • Flaggers and signage will be provided to direct pedestrians and traffic.

WCUP Crain

For questions and concerns please reach out to John Barlow, project consultant jbarlow@uchicago.edu.


Prioritized Crosswalk Enhancements

August 28, 2025

The last activity for this project is the installation of the speed feedback signs and RRFBs. The crosswalk locations noted to receive the RRFB system on the graphics below were determined based on CDOT requirements and traffic study information. There are some components that make up the flashing beacon system that currently have a longer than typical lead time. While installation efforts will begin this week, the project is slated to have all crosswalks with this added signage feature operational before the end of November. 

55th street graphic

Croswalk graphic

For questions and concerns, please reach out to Lindsay Haskins,  Project Manager, lhaskins@uchicago.edu


Quantum Lab Renovation - Michelson Center for Physics

August 19, 2025

The Mason Lab retrofits existing dry lab space to support quantum materials research, with a focus on the electronic properties of nanoscale and correlated systems, such as nano-scale wires, atomically thin membranes, and nanostructured superconductors. This work will entail the installation and reconfiguration of MEP infrastructure, casework, and minor finishes upgrades.

Schedule:

  • Start: Friday, August 29, 2025
  • The work will happen in 2 phases and will continue through the end of February 2026.
  • The work will mostly be contained within the rooms and areas of construction, with some work occurring in the corridor  

Construction Impacts/Disruptions: Throughout the project, building occupants and visitors can expect the following:

  • Construction Noise and some vibration impact of sawing, hammering, etc. should be expected.
  • Workers will be on site from 6 a.m. to 4 p.m. Mondays – Saturdays
  • A few sprinkler heads in the area of work will need to be relocated, which will require a drain down of the sprinkler line in the basement for one 8-hour shift. The rest of the building will remain unaffected.

Lab project graphic

For questions and concerns, please reach out to Krystal McDoom, Project Manager, kmcdoom@uchicago.edu


6022 S. Drexel Hot Water Heat Exchanger Replacement

August 13, 2025

This project will include the installation of three new gas-fired domestic water heaters, associated accessories, and vertical ventilation pipes on the south exterior elevation. Once the new equipment is in place and operational, Facility Services will be mobilizing a construction project for the above location. Please see below for the schedule and anticipated impacts. Demolition and removal of the existing steam-powered domestic water heater and storage tank will take place.

Schedule:

Start: On August 18th, 2025,
The work will continue through the middle of November 2025. 

Construction Impacts/Disruptions: Throughout the project, building occupants and visitors can expect the following:

  • Construction activities are expected between 8 am and 4 pm, Monday through Friday, for the duration of the project.

  • Construction activities will occur in the basement level hallway and mechanical spaces, as well as the south exterior elevation.

  • Occupant access to the building and community areas in the basement will be maintained throughout construction.

  • There will be periods of significant noise inside the building associated with work activity. Noise will include drilling, sawing, and banging.

  • A limited-duration scheduled water service disruption is expected when transitioning to the new system.

  • A community notification will be sent to occupants a minimum of 72 hours in advance of this activity.  

  • Debris dumpsters will be located in front of the building as indicated on the graphic below.

6022 Drexel project graphic

For questions and concerns, please reach out to Crystal Szewczyk, Project Manager, ccarlson2@uchicago.edu


Crerar Quad Vault Improvments

July 29, 2025

Work temporarily paused for this project during Orientation week and the week leading up to the South Side Science Festival. We will resume construction of this project on Monday, October 6th. The footprint for the project fencing will remain minimized, and pedestrian paths will still be open, as shown in the graphic below. We have run into a lead time issue for one of the final steps for this project, and this is the driver for the new project’s completion date.

Remaining Schedule:

  • Work will resume on Monday, October 6th
  • Concrete pours for the two hatch lids are slated for Saturday, October 11th, so that there is less impact on pedestrians.
  • The remainder of the electrical scope is slated for October 14th and 15th
  • Plumbing and mechanical vault work to be completed by October 30th.
  • Fencing removal and landscaping restoration are slated for Monday, November 3rd.


For questions and concerns, please reach out to Lindsay Haskins,  Project Manager, lhaskins@uchicago.edu


Harper Library - Alterations to Accessible NE Entrance

June 9, 2025

The project will reconfigure the existing accessible NE entrance and vestibule doors to provide wider accessible openings with new automatic door operators, including push-plate actuators and card readers. The work will occur on the first floor exterior and interior areas of the existing NE entrance and vestibule.

Schedule:

Start:  Wednesday, June 11th, 2025
The work will continue through middle of August 2025.  

Construction Impacts/Disruptions: Throughout the project, building occupants and visitors can expect the following:

  • Impact on NE Entrance ingress/egress and accessible route
  • Workers will be on site from 6 a.m. to 2:30 p.m. each day
  • Noise and Vibration impact from 6 a.m. to 2:30 p.m. each day

Harper ADA Entrance Graphic

For questions and concerns, please reach out to: Bryndis Pape, Project Manager CPD at bpape1@uchicago.edu.


William Eckhardt Research Center Lab Renovations

May 19, 2025

The project includes enabling renovation work required in LL1-130 and LL1-148 for the researcher (Carlstrom Team) who currently occupies LL1-127. This will free space for the LL1-127 renovations to accommodate a new researcher (Fleming Team) with different requirements.  The project will be constructed in two phases: the first phase starting with LL-130/LL148 June 2nd through mid-July, and the second phase, starting with LL-127 from mid-July through October 2025.

Construction Impacts and Disruptions:

  • Phase I has been completed
  • Phase II: The Unistrut installation has been completed. Crane installation began on September 11th. Lab LL127 to be ready by mid-October.
  • During Phase II, minor vibration could be experienced during the installation of the crane and mezzanine, for which advance notification shall be provided to adjacent labs located on the same floor, above, and below.  Such work will be limited to a shorter duration, and the construction crew shall strive to do the work before regular business hours.
  • No impact on accessibility pathways throughout construction.
  • Work hours will start at 5:30 am through 2:30 pm, with possible overtime based on schedule constraints. 

WERC Lower Level lab graphic

For questions and concerns, please reach out to Carlos Martinez, Project Manager, cimartinez@uchicago.edu.


Accelerator Building (ACC) and High Energy Physics (HEP)-Demolition

September 3, 2024

Starting on Monday, Sept. 9, construction activities will start at the North Sciences Quad in preparation for the demolition of the HEP and ACC buildings. The work activities will continue for several months into early 2025. There will be periods of time when noise, dust and vibrations will be evident, and mitigation efforts will be managed by the construction team. Please see the below graphic showing the fenced-in project site and expected traffic and pedestrian interruptions.

The campus community can expect the following during the coming months:

  • Traffic lane and parking lane temporary closures.
  • Saw-cutting for water disconnecting work in the roadway on Ellis Avenue.
  • Construction vehicle traffic during fence installation and throughout demolition.

Demo graphic

For questions, please contact Eric Eichler, project consultant, at eeichler@forgeprojects.com

Thank you for your patience throughout this project.


Rockefeller Chapel Exterior Envelope project-summer 2024

February 6, 2024

A project to repair the façade and restore the stained-glass windows is scheduled to start in early February. The project will mobilize throughout the month of February with actual construction starting in early March. The project schedule will continue through April 2026. 

The campus community can expect the following throughout the project:

  • There will be scaffolding and fencing erected throughout the project. 
  • All access to the chapel will remain open.
  • The circle at the east side of the chapel will remain open for drop-offs.
  • There will be debris dumpsters at the site.
  • Workers will be on site Monday through Friday from 7 a.m. to 4 p.m.
  • There will be some noise associated with project activities.

Rockefeller Construction Graphic

Please direct questions to Patrick Lummen, project manager, at plummen@uchicago.edu.

Thank you for your patience during this work.


How Do I?

UChicagoSocial: Facilities Services