Tunnel repairs at 59th and Woodlawn

July 20, 2017

Click here for the formal notification.

The campus community can expect the following:

  • Parking restrictions and one-lane traffic along 59th Street.
  • Fencing will be in place surrounding the construction site.
  • Sidewalk along 59th Street (east/west) will be closed during phase 2.
  • Signage will be in place during each phase to direct pedestrians.
  • Buses and shuttle routes will remain open.
  • The crosswalks at 59th Street and Woodlawn Avenue will remain open and accessible.
  • Completion is by Friday, Sept.15, weather permitting.

For questions, please contact Daniel Albo, project manager at dalbo@uchicago.edu or 773.612.8179.