Main Quadrangle-panel replacement project

August 10, 2017

Click here for the formal notification.

On Monday, Aug. 7, sections of pervious panels will be replaced in the main quadrangle.

The campus community can expect the following:

  • Working hours are 8 a.m. to 2 p.m.
  • Noise will be intermittent when equipment is in use.
  • Trucks will be on site each day.
  • Building access will be maintained at all times.
  • Completion is by Friday, Sept. 15, weather dependent.

Please direct questions to Denise Davis, project manager at ddavis3@uchicago.edu or 773.405.3810.