Eckhart Hall Reroofing

June 7, 2018

At 6 a.m. on Monday, June 11, installation of scaffolding at the east and north elevations of Eckhart Hall will start. Following the installation, reroofing activity will start and continue into October.

  • The campus community can expect the following throughout construction:
  • Walkways to the building will remain accessible.
  • Updates on impactful activities will be provided.
  • At times there will be noise generated by construction activity. 
  • The daily work schedule is 6 a.m. to 2:30 p.m., Monday through Friday.
  • Working hours may vary throughout the summer, including early start times and weekend work.
  • Scheduled completion of phase 2 is by Friday, October 19, weather permitting.

Please direct questions to Barry O’Quinn, project manager, at boquinn@uchicago.eduor 773.691.7965.

Thank you for your patience throughout this project. 