Cobb Hall-classroom renovation

June 11, 2018

Cobb Hall-classroom renovation

Project schedule: 6/11/18 through ~9/14/18

·Scope/impact: all classrooms on floors 1, 3 and 4 will be repainted and carpet and furniture will be replaced; floors 1 through 4 will get all new video systems installed; floors 2 and 3 furniture removal and replacement through lower level ramp and 1st floor thru the north entrance.

·Daily work schedule: 6 a.m. and 3 p.m. (no weekend work planned at this time)

·Street use: parking spaces blocked-off on east side of Ellis Avenue in front of Cobb Hall.

·Construction supervision will be provided throughout this project.