Cobb Hall-Air Handler Unit C (AHU-C) replacement

Project schedule: 6/11/18 through ~8/31/18

  • Scope/Impact: all classrooms and main corridors will not have cooling; minimal noise; contractor will use elevator between lower level and 5th floor; tool boxes and material will be stored in the 5th floor lobby; no building-wide cooling shutdowns are planned, cooling will remain in office spaces.
  • Daily work schedule: 6 a.m. and 3 p.m. (no weekend work planned at this time)
  • Street use: parking spaces blocked-off on east side of Ellis Avenue in front of Cobb Hall.