5730 S. Woodlawn Avenue Development Innovation Lab

May 17, 2021

Construction activities will start the week of May 17th at 5730 S. Woodlawn Avenue for the build-out of the Development Innovation Lab. A graphic showing the building location, the construction route to the building, and the placement of the debris dumpster is shown below.

The campus community can expect the following:

  • Remodeling of interior space.
  • Installation of interior finishes, including but not limited to millwork, flooring, paint, etc.
  • Associated mechanical, electrical, and plumbing work will also be performed.
  • Furniture installation  
  • Working hours are 8 a.m. to 6 p.m., Monday through Friday, and weekend work, as needed.
  • Completion is by end of August 2021.

Click here for the Facilities Services statement of protocols to address the challenges presented with the COVID-19 pandemic for construction and vendors working in buildings and at construction sites.

Please direct questions to Krystal McDoom, Project Manager, at kmcdoom@uchicago.edu or 773.236.7199. 