| Project Name: | MATH-STAT RENOVATION |
| Project Scope: | Complete renovation of the Math-Stat building interior and exterior. |
| Contact: | Chris Jackson, 773-612-3850 |
| Construction Start Date: |
August 1, 2009 |
| Completion Date: | December 2010 |
| Degree of Disruption: |
During the months of June and July the building will be vacated. The construction contractor will begin mobilizing at the end of July. |
| Mitigation Efforts: | There will be noise and dust at times; all construction on this project will be completed behind the construction fence and scaffolding that surrounds the building. To alleviate traffic congestion on University Avenue, the project site will be accessed via the alley between University and Woodlawn Avenues. |