Mansueto Library Paver Project, northeast Quad Paver Project, Admin Bldg Main Quad Paver Projects Main Quad Paver Projects Main Quad Paver Projects Paver Project, Rockefeller Chapel Quad Pedestrianization Jones Facade Restoration Math-Stat Renovation Center for Gender/Race Studies Roof Renovation Pick Hall Chilled Water Project Gates-Blake Riser Replacements & Restroom Remodeling Harper Library Ramp Installation Social Science Research Portico Foster Facade Partial Restoration Midway Crossings
Project Name: HARPER LIBRARY
ADA Ramp Installation
Project Scope: Provide new concrete ramp and power door operators at East Tower entrance.
Contact: Rob Kelly, 773-504-5037
Construction
Start Date:
June 15, 2009
Completion Date: July 15, 2009
Degree of
Disruption:
Minimal; work to take approximately  one to three weeks.
Mitigation Efforts: Area fencing to separate work/public zones